13.12.2011



 Boiler  Type F6 Foundation - Cast Saturday 19th November - Curing 



B01 Boiler Type F3 Foundation - Installation of Thermocouples  
           complete. Form work & Temporary Works in Progress.

                  B01 Pulveriser & Bunker Bay Steel Structure Pile Caps 
                    - Steel Fixing in progress.

B07 Fabric Filter - De-watering works

B07 Fabric Filter - Preparation for Lean Concrete


    Positioning of Sino Hydro Piling Ring @ B63 Polishing Plant Chemical Tank.