Consortium Office -Alstom.

Consortium Office -CMC -Laying Of Bricks -Grd.Floor.

Type F3 -Foundation -Boiler -West Side-Scheduled For Concreting @15.12.2011 @550m3.

Steel Reinforcement -Type 3 -Foundation -Bunker/Mill -B11 -BB.

PDA -Pile # T057-1000mm dia. -Turbine Hall.

PDA -Pile # T057 -1000mm dia. -Turbine Hall -Witnessed By TNBJ/OE.

Bar Cutting & Bending For Bunker/Mill -Type 2 & Type 3 -Foundations.

Steel Fixing -Bunker/Mill -Type 3 Foundation-B11-BB.

Steel Fixing -Bunker/Mill -B13-BB -Type 3 -Foundation.

BOP -Chimney -Preparation For MLT -Scheduled On 15.12.2011.

Lean Concreting To Fabric Filter -Pile Caps.

Lean Concreting - Fabric Filter -Pile Caps.