Hacking Of Piles -Fabric Filter /Total Piles To Be Hacked =50piles.
PIT -Bunker/Mill -26points.
Steel Fixing -Type 2 -Foundation -B17-BA -Bunker/Mill.
Steel Fixing -Type 2 Foundation -B17-BB -Bunker/Mill.
PIT -Pile #T288 -1000mm dia. -Turbine Hall.
PIT -Bunker/Mill -26points.
Bar Cutting & Bending For Fabric Filter Foundations.
Excavation To Type F1 -Foundation -Boiler -East Side.
Installation Of Steel Reinforcement -Pedestal -Type F3 -Foundation -Boiler -West Side.
Installation Of Steel Reinforcement -Pedestal -Type F3 -Foundation -Boiler -West Side.
Pre-Pour Inspection By TNBJ/OE -Type F3 Foundation -Boiler -West Side.
Pre-Pour Inspection -Type F3 -Foundation -Boiler -West Side.