31.12.2011

F2 -Boiler -East Side -Curing In Progress.

F1 -Boiler -East Side -Steel Fixing Ongoing.

F6 -Boiler -West Side -Backfilling & Compaction In Progress.

F3/F6 -Boiler -West Side -Backfilling & Compaction In Progress.

Bunker/Mill -B9 -BB-Installation Of Formwork.

Bunker/Mill -B7-BA -Steel Fixing In Progress.

Turbine Hall -Excavation 1st Phase In Progress.

Turbine Hall -Excavation 1st Phase In Progress.

Turbine Hall -Excavation -1st Phase In Progress.

Concreting To Pile #QA47 -1000mm dia. -CWP -BOP -SinoHydro.

F6 -Boiler -East Side- Hacking Of Piles Ongoing.

F2 -Boiler- East Side.

Crushing Of Cut Piles -EconPile -F1 Foundation -Boiler -West side.

BOP -CMC/MCB -Sub-Station -Project Power Supply -Base Slab Preparation.

30.12.2011

Fabric Filter -Steel Fixing -Tie Beam.

Carting Away Of Debris -(Hacked Piles) -F1 Foundation -Boiler -West Side.

F3 -Boiler -East Side- Preparation For Lean Concrete.

F3 -Boiler -East Side. -Preparation For Lean Concrete.

Bunker/Mill -B9 -BA/BB.

Bunker/Mill -B9 -B7 -BA -Installation Of Formwork.

Bar Cutting & Bending Yard -Bunker/Mill.

Turbine Hall -Excavation -1st Phase In Progress.

Turbine Hall -Excavation 1st Phase In Progress.

BOP -MCWS -Backfilling In Progress.

BOP-MCWS -Preparation To Commence With Piling Works -Spun Pile.

BOP -MCWS -Backfilling In Progress.

BOP -MCWS -Preparation To Commence With Spun Pile.

29.12.2011

Consortium Office -Alstom.

Weekly -EHS -Tool Box Meeting.

Consortium Office -Alstom -Grd.Floor.

Consortium Office -Alstom -Grd. Floor.

Fabric Filter -Steel Fixing -Tie Beams.

F2 -East Side -Installation Of Formwork -Scheduled For Concreting On 30.12.11 @75m3.

F3-Boiler -East Side -Preparation For Lean Concreting.

F1 -Boiler -West Side- Hacking Of Piles (10-nos) Ongoing.

F3/F6 -Boiler -West Side -Backfilling & Compaction Ongoing.

F3/F6 -Boiler -West Side -Bakfilling /Compaction In Progress.

Bunker/Mill -B9 -B7 -BA -Steel Fixing.

Curing -Bunker/Mill -B17 -B13 -Type 2/Type 3/Type 3A/Tie Beams -BA/BB.

Fabric Filter -Steel Reinforcement -Tie Beams.

F6 -Boiler -East Side -Lean Concreting.

27.12.2011

F1 Foundation -Boiler -West Side -Lean Concrete Completed.

Installation Of "Hyrib" -Construction Joint -B13 -BB -Bunker/Mill.

Installation Of Steel Reinforcement -Stump -B13 -BA -Bunker/Mill.

Final Inspection Prior Concreting -Bunker/Mill -B17-B13 -BA/BB.

Final Inspection Prior Concreting -Bunker/Mill -B17-B13 -BA/BB.

F1 Foundation -Boiler -West Side -Hacking Of Piles.

Final Cleaning Prior Concreting -Bunker/Mill -B17 -B13 -BA/BB.

Fabric Filter -Lean Concrete To Pile Caps.

26.12.2011

Consortium Office.

Steel Cages -Preparation -Chimney -BOP -EconPile.

F2 Foundation -Boiler -East Side -Steel Reinforcement Completed.

F2 Foundation -Boiler -East Side -Steel Reinforcement Completed.

Steel Fixing -Stump -Type 3A Foundation -B13-BB -Bunker/Mill.

Concreting To Pile # QA17 -1000mm dia. -CWP -Turbine Hall -BOP -Sinohydro.

Steel Fixing -Stump -Type 2 Foundation -B17 -BA -Bunker/Mill.

Steel Fixing -Type 3 Foundation -B9 -BA -Bunker/Mill.

Pile # A04 -BUnker/Mill -Type 2 Foundation -B3-BB -Brickwall Formwork.

Concreting To Pile #A10 -800mm dia. -Slag Conveyor.