10.12.2012

F10-B4 -Boiler -West Side -Hacking Of Piles In Progress (12nos).

F6 -Boiler -West Side -Steel Fixing -Stump.

F6-Type A -Boiler -West Side -Ready For Concreting.

F11-B14 -Boiler -East Side -Inspection Of Steel Reinforcement -Bottom Layer.

F11-B14 -Boiler -East Side -Steel Reinforcement.

F11 -B14 -Boiler -East Side -Inspection Of Steel Reinforcement -Bottom & Top Layer.

Mill -H -Final Setting To J-Bolts Prior Inspection.

Turbine Hall -Sheet Piling -Condensate Sump Pit.

F3 -Boiler -West Side -Inspection of Steel Reinforcement -Stump.

Turbine Hall -Lean Concrete Preparation -Grid 8 -Grid -7 -B/D.(-3.6MLSD).

Turbine Hall -Condensate Sump Pit -Excavation In Progress -Down To Level (-7.2MLSD).

F4 -Type-A -Boiler -West Side -Steel Fixing In Progress.

09.02.2012

F4 -Type A -Boiler -East Side -Steel Fixing In Progress.

F6 -Type A -Boiler -East Side -Final Preparation Prior Concreting.

F10-B4 -Boiler -East Side -Hacking Of Piles (12nos) In Progress.

F1-B4 -Boiler -West Side -Curing In Progress.

Mill -H -Preparation To Install J-Bolts.

F11-B14 -Boiler -East Side -Steel Reinforcements -Top Layer.

Turbine Hall -Sheet Piling To Condensate Sump Pit In Progress.

Mill -H -Pedestal -Installation Of J-Bolts In Progress.

Mill-H -Installation Of J-Bolts In Progress.

Mill-H -Installation Of -J-Bolts In Progress -8nos.

Turbine Hall -Excavation -3rd Stage -Down To Level (-3.6MLSD).

Turbine Hall -Gridline 8 -Gridline 6 -B/D -Preparation For Lean Concrete -(-3.6MLSD).

08.02.2012

Final Inspection -F1-B4 -Boiler -West Side -Prior Concreting.

F4-Type-A -Boiler -Steel Fixing In Progress.

F4 -Type-A -Boiler -Steel Fixing In Progress.

Pre-Inspection -Steel Reinforcements -Stump -F3-Foundation -Boiler -West Side.

Pre-Inspection -J-Bolts -Stump -F6 -Foundation -Boiler -West Side.

F6 -Type A -Boiler -West Side -Final Preparation Prior Casting.

F10-B14 -Steel Fixing -Bottom Layer In Progress.

Turbine Hall -Preparation For 3rd Stage Excavation -Down To Level (-3.6MLSD).

Turbine Hall -Grid -8 -Grid -9 -B/D -Preparation For Lean Concrete (-3.6MLSD).

Boring To Pile#HN54 -1200mm dia. -Chimney -BOP -EconPile.

Boring To Pile #HN44-1200mm dia. -Chimney -BOP -SinoHydro.

Concreting To Pile #HN54-1200mm dia. -Chimney -BOP -EconPile.

F1-B4 -Boiler -West Side -Concreting In Progress.

F11 -B4 -Boiler -West Side -Lean Concreting In Progress.

07.02.2012

Steel Cage Installation -Pile #HN36-1200mm dia. -Chimney -BOP -SinoHydro.

Boring To Pile #HN08-1200mm dia. -Chimney -BOP -EconPile.

F1 -Foundation -Boiler -West Side -Steel Fixing -Stump.

Crushing Of Hacked Piles -Boiler.

F4-Foundation-Type A -Boiler -East Side -Preparation For Steel Fixing.

F10-B14 -Foundation -Boiler -East Side -Steel Fixing -Bottom Layer In Progress.

F11-B4 -Foundation -Boiler -West Side -Excavation In Progress.

F6 -Boiler -West Side -Cleaning Prior Formwork Installation.

F6 -Foundation -Boiler -West Side -Hacking Works (Construction Joint -Stump).

F6 Foundation -Type -A -Boiler -West Side -Formwork Installation.

F10 -B14 -Boiler -East Side -Steel Fixing -Bottom Layer In Progress.

Mill-H -Installation Of Formwork.

Mill-H -Installation Of Formwork.

Turbine Hall -Excavation-3rd Stage Down To Level (-3.6MLSD).

Turbine Hall -Excavation 3rd Stage In Progress (-3.6MLSD).

CEB -Hacking Of Piles In Progress -Gridline -2 -A/G.

CEB -Preparation For Lean Concrete -Grid 1 -A-G.

F4-Type-E -Boiler -East Side -Curing In Progress.