09.04.2012

 Chimney-Steel Fixing of Top Bars and Formworks Installation of Base Foundation in Progress
Fuel Gas Duct-Duct Pipes-Excavation of Bored Piles in Progress
 F10-Boiler-Cleaning Prior for Steel Fixing of Base Foundation
 F5-Boiler-Final Preparation of Stumps Prior for Concreting
 F9-Boiler-Removal of Stump Formworks
F11-Boiler-Casting Completed and Curing in Progress
 F4-Boiler-Removal of Formworks in Progress
Boiler Ash Pit- Final Preparation Prior for Final Pour
 Mill D-Mechanical-Scaffolding Erection in Progress
 Mill A & B-Retaining Wall-Formworks Removal in Progress
Mill H-Mechanical-Packer Plates Installation in Progress
 Ash Hopper-Boiler-Preparation Prior for Lean Concreting
 Turbine Hall-South Side-Preparation Prior for Hacking of Bored Pile
 Turbine Hall-East Side-Box Tie In Installation in Progress
Turbine Hall-Tower Crane Installation in Progress
 Central Electrical Building- Formworks Installation in Progress
 Central Electrical Building- Steel Fixing Installation in Progress
 Phase 1-Main Cooling Water-Excavation and Cutting of Spun Piles in Progress
 Phase 1-Sea Water Fuel Gas Desulfurization-Glass Reinforced Pipes-Compaction in Progress