Fuel Gas Duct-Duct Pipes-Excavation of Bored Piles in Progress
F10-Boiler-Cleaning Prior for Steel Fixing of Base FoundationF9-Boiler-Removal of Stump Formworks
F11-Boiler-Casting Completed and Curing in Progress
F4-Boiler-Removal of Formworks in Progress
Boiler Ash Pit- Final Preparation Prior for Final Pour
Mill D-Mechanical-Scaffolding Erection in ProgressMill A & B-Retaining Wall-Formworks Removal in Progress
Mill H-Mechanical-Packer Plates Installation in Progress
Ash Hopper-Boiler-Preparation Prior for Lean ConcretingTurbine Hall-South Side-Preparation Prior for Hacking of Bored Pile
Turbine Hall-East Side-Box Tie In Installation in Progress
Turbine Hall-Tower Crane Installation in Progress
Central Electrical Building- Formworks Installation in ProgressCentral Electrical Building- Steel Fixing Installation in Progress
Phase 1-Main Cooling Water-Excavation and Cutting of Spun Piles in Progress
Phase 1-Sea Water Fuel Gas Desulfurization-Glass Reinforced Pipes-Compaction in Progress