10.04.2012

Chimney-Steel Fixing of Top Bars for the Base Foundation in Progress
 F4-Boiler-Formworks Installation of Stumps in Progress
 F5-Boiler-Final Preparation Prior for Concreting in Progress
 Ash Hopper-Casting of Lean Concrete Completed and Preparation for Steel Fixing
 F8-Boiler-Steel Fixing of Base Foundation in Progress
 F10-Boiler-Steel Fixing of Base Foundation in Progress
F9-Boiler-Backfilling in Progress and Formworks Installation of Stumps in Progress
 Mill-Mechanical-Packer Plates Installation in Progress
 Mill F to H-South Side-Backfilling in Progress
Mill C-Mechanical-Scaffolding Erection in Progress
 Turbine Hall-South Side-Excavation in Progress
 Turbine Hall-South Side-Preparation Prior for Lean Concreting
Turbine Hall-South Side-Hacking of Bored Piles in Progress
 Central Electrical Building-Steel Fixing of Column Starter Bar in Progress
 Central Electrical Building-Preparation Prior for Lean Concreting  in Progress