Chimney-Steel Fixing of Top Bars for the Base Foundation in Progress
F4-Boiler-Formworks Installation of Stumps in ProgressF5-Boiler-Final Preparation Prior for Concreting in Progress
Ash Hopper-Casting of Lean Concrete Completed and Preparation for Steel Fixing
F8-Boiler-Steel Fixing of Base Foundation in Progress
F10-Boiler-Steel Fixing of Base Foundation in Progress
F9-Boiler-Backfilling in Progress and Formworks Installation of Stumps in Progress
Mill-Mechanical-Packer Plates Installation in ProgressMill F to H-South Side-Backfilling in Progress
Mill C-Mechanical-Scaffolding Erection in Progress
Turbine Hall-South Side-Excavation in ProgressTurbine Hall-South Side-Preparation Prior for Lean Concreting
Turbine Hall-South Side-Hacking of Bored Piles in Progress
Central Electrical Building-Steel Fixing of Column Starter Bar in Progress
Central Electrical Building-Preparation Prior for Lean Concreting in Progress