Boiler East - Civils preparing area for Steel erection
Ground being raised between Boiler F2 pedestals
Boiler F10 Rebar
Boiler F8 Rebar
Boiler Ash Hopper (SSC)
Boiler F4 pedestals
Mill H packing plates
Mill G Scablling
STH Formwork removal
STH excavation works- south side
STH Rebar works- west side
New HV line - 1/5 tower erection
SWFGD trench for GRP under new HV line
Excavation and blinding works in MCW trench beneath New HV line
Central Electrical Building foundations