Chimney-Steel Fixing Top Bar of the Base Foundation in Progress
Fuel Gas Duct-Pipe Ducts-Preparation of Bored Pile Surrounding Prior for Concreting
F11-Boiler-Formworks Installation of Stumps in ProgressF4-Boiler-Final Preparation of Stumps Prior for Concreting and Backfilling in Progress
F9-Boiler Final Preparation of Stumps Prior for Concreting
GL BK-BM / GL B9-B12.5-Boiler- Backfilling in Progress
Mill-South Side-Backfilling in Progress
Mill B-Mechanical-Scaffolding Erection in Progress
Turbine Hall-West Side-Steel Fixing of Base Foundation in ProgressTurbine Hall-North Side-Steel Fixing of Ground Walls in Progress
Turbine Hall-South Side-Excavation in Progress
Central Electrical Building-GL A-G / GL 2- Final Preparation on Base Foundation Prior for Concreting in ProgressCentral Electrical Building-GL A-G / GL 3- Steel Fixing of Base Foundation in Progress
Boiler-East Side-Mechanical-Temporary Laydown Area for Boiler Steel Structure
Phase 1-Main Cooling Water-Preparation Prior for Steel Fixing of Base Foundation in ProgressPhase 1-Seawater Fuel Gas Desulfurization Glass Reinforced Pipes-2nd Layer-Backfilling and Compaction in Progress
New HV Line-Pylons-Near Existing Switchyard-Steel Frame Erection in Progress
New HV Line-Pylons-Inside 25 year Ash Pond-Steel Fixing of Base Foundation in Progress