PIT -Fabric Filter -25points.

Steel Reinforcement -Foundations -Fabric Filter.

Steel Fixing -Tie Beam -Bunker/Mill -B15 -B13 -BB.

Installation Of Formwork -Tie Beam -Bunker/Mill -B17 -B15 -BB.

Chipping & Cleaning -Surface Preparation -Construction Joint -Bunker/Mill -1st Phase Foundation.

Delivery Of Sheet Piles -Preparation For Coffer Dam -F3/F6 -Boiler -East Side.

Dismantling Of Formwork -F6 Foundation -Boiler -West Side.

Dismantling Of Formwork -F6 Foundation -Boiler -West Side.

Applying Of Curing Compound -F6 Foundation -Boiler -West Side.

PDA Test -Pile # A22 -800mm dia. -Fabric Filter.