19.12.2011

Fabric Filter -Lean Concrete -Tie Beams.

F2 Foundation -Boiler -East Side -Preparation For Pile Hacking / Lean Concrete.

Sheet Piles -Preparation For F1 Foundation -Boiler -West Side.

Steel Reinforcement -Fabric Filter -Foundations.

Steel Fixing -Tie Beam -Bunker/Mill -B17 -B13 -BA.

Steel Reinforcement -Tie Beam -Bunker/Mill -B17 -BA -BB.

Chipping For Construction Joint -Bunker/Mill -1st Phase Foundation -B3.

Inspection -Steel Reinforcement -Tie Beams -Bunker/Mill -B17 -B13 -BA / BB.

BOP -Chimney -Steel Cages Preparation For Bore Pile -1200mm dia.-EconPile.

Consortium Office -Alstom -Grd.Floor.

Consortium Office -Alstom -Grd. Floor.

Consortium Office -Alstom -Grd. Floor.

Consortium Office -Alstom -1st Floor.

Consortium Office -Alstom -1st Floor.