17.11.2011

Consortium Office.

Weekly EHS Tool Box Meeting -ALSTOM/CMC/MCB/GIGA.

Boring To Pile #B12-800mm dia. -FGD -EconPile -Last Point For EconPile.

Excavation -Boiler Type F3 -Foundation -West Side.

Steel Fixing -Bunker/Mill -1st Pour Foundation -B9.

Bunker/Mill -Pile Cap -B15.

Boiler -Type F3-West Side -Foundation -Excavation In Progress. -

Boiler -Type F3-West Side- Foundation -West Side -Excavation In Progress.

Steel Fixing/Formwork -Bunker/Mill -1st Pour Foundation -B9.

Steel Fixing -Bunker Mill -1st Pour Foundation -B11.

Cleaning Of Debris -Hacked Piles -Bunker/Mill -B15.