16.11.2011

Boring To Pile #B11-800mm dia. -FGD -EconPile.

Installation Of Dewatering Pipes -Boiler -North/East Side.

Sheet Piling -Boiler -Type F3/F6 -Foundation -West Side -Preparation For Coffer Dam.


Hacking Of Piles -Bunker/Mill -Foundation -B15.

Boiler -Type F3/F6 -Foundation -West Side -Excavation In Progress.

Consortium Office -Installation Of Purlins -Roofings -In Progress.

Consortium Office -Alstom -Laying Of Bricks -Grd. Floor.

Consortium Office -Alstom -Concreting To Appron Slab.

Steel Fixing -Bunker/Mill -1st Pour Foundation -B9.

Steel Fixing -Bunker/Mill -1st Pour -Foundation -B9.

Installation Of Steel Cage -Pile #B32-800mm dia. -Main Control Building -SinoHydro.

Boring To Pile #B38 -800mm dia. -Main Control Building -SinoHydro.