15.11.2011

Consortium Office -Alstom -Laying Of Bricks -Grd. Floor.

Installation Of Dewatering Pipes -Boiler -East Perimeter -87/120 points.


Installation Of Dewatering Pipes -Boiler -East Perimeter.

Sheet Piling To Boiler -Type F3/F6 -Foundation -Preparation Of Coffer Dam.

MLT -In Progress -Pile #B57-1200mm dia. -Boiler.1141Ton.

Hacking Of Piles -Bunker/Mill -B13.

Pile Cap -Bunker/Mill -B9 -Pending PIT -Proceed With Steel Reinforcement Installation.

Preparation Of Bar Bending Yard -Boiler -Type F3/F6 -Foundations.

Excavation For Dewatering Discharge Drainage(Boiler -North Side) To Silt Trap Area.

Concreting To Pile #B08 -800mm dia. -FGD -EconPile.

Concreting To Pile #B16 -800mm dia. -FGD -EconPile.

14.11.2011

Consortium Office -Alstom -Laying Of Bricks In Progress.

Hacking Of Piles -Bunker/Mill -B11.

Bunker/Mill -B9 -Preparation For PIT & Steel Reinforcement Installation.

Applying Of Curing Compound -Bunker/Mill -1st Pour Foundation -B7.

Applying Of Formwork Oil -Preparation For Bunker/Mill -1st Pour -B9.

Lean Concrete -Bunker/Mill -B13.

Excavation To Boiler Area -East Side.

Installation Of Dewatering Pipes -Boiler -East Perimeter -87/120 Points Completed.

Consortium Office -Laying Of Bricks In Progress.

Consortium Office -Alstom -Laying Of Bricks In Progress.

Consortium Office -Alstom -Laying Of Bricks/Installation Of Door Frames/Preparation Of Mock-Up Unit In Progress.


Concreting To Pile #B15-800mm dia. -FGD -Econpile.

MLT -Pile #B57 -1200mm dia. -Boiler In Progress -1141Ton.

MLT -Pile #B57 -1200mm dia. -Boiler -In Progress =1141Ton.

Site Office -Murray Robert -Off-Shore Works/Water Intake.

Sheet Piles -Preparation Works -Water Intake/Off-Shore Works -Murray Robert.

12.11.2011

Consortium Office -Alstom -Brick Laying /Installation Of Trusses/Purlins/Frames In Progress.

Consortium Office -Alstom -Preparation Of Mock-Up Unit -Grd. Floor.

Consortium Office -Alstom -Preparation Of Mock-Up Unit -Grd. Floor.

Consortium Office -Alstom -Preparation Of Mock-Up Unit -Grd. Floor.


Boring To Pile #B07-800mm dia. -FGD Building. -EconPile.

Boring To Pile #B13 -800mm dia. -FGD Building. -EconPile.

Bore Rig -HR240 -Hydraulic -Dismantling For Demobilization -EconPile.


MLT -Pile # B57 -1200mm dia. -Boiler -To Commence On 14.11.2011 -1141Ton. -EconPile.

Concreting To Pile #T249 -1000mm dia. -Turbine Hall -SynoHydro.

MCB -Area -Preparation To Commence With Bore Pile Works -800mm dia. -96Points -SynoHydro.

BOP -MCWS -Backfilling In Progress.

11.11.2011

Laying Of Bricks -Consortium Office -Alstom -Grd.Floor -Wash Rooms.

Brickworks -Consortium Office -Alstom -Wash Rooms.

Hacking Of Piles -Bunker/Mill -B9.

Preparation For Lean Concrete -Pile Cap -Bunker Mill -B15.

Consortium Office -Alstom -Preparation For Mock-Up Unit In Progress.

Sheet Piling -Boiler Area -Preparation For Coffer Dam -Type F3/F6 Foundation.

Sheet Piling -Preparation For Coffer Dam -Boiler Area -Foundation Type F3/F6.

Hacking Of Piles -Bunker/Mill -B9.

Lean Concreting In Progress -Pile Cap -Bunker/Mill -B13.

Lean Concreting In Progress -Pile Cap -Bunker/Mill -B15.

09.11.2011


Installation of secondary Steelwork to Block 1 (Alstom) of EPC office.

Curing of 1st Phase pour Mill C & Steel fixing on Mill D.

1st Phase, Mill A ready to pour. ( 48m3)

Curing and concrete finishing to 1st phase pour Mill B.


Blinding on Mill E


Econ Pile - Boiler Electrical Building (B35)

Econpile - Piling on FGD Electrical Building (B37)