09.11.2011


Installation of secondary Steelwork to Block 1 (Alstom) of EPC office.

Curing of 1st Phase pour Mill C & Steel fixing on Mill D.

1st Phase, Mill A ready to pour. ( 48m3)

Curing and concrete finishing to 1st phase pour Mill B.


Blinding on Mill E


Econ Pile - Boiler Electrical Building (B35)

Econpile - Piling on FGD Electrical Building (B37)