12.11.2011

Consortium Office -Alstom -Brick Laying /Installation Of Trusses/Purlins/Frames In Progress.

Consortium Office -Alstom -Preparation Of Mock-Up Unit -Grd. Floor.

Consortium Office -Alstom -Preparation Of Mock-Up Unit -Grd. Floor.

Consortium Office -Alstom -Preparation Of Mock-Up Unit -Grd. Floor.


Boring To Pile #B07-800mm dia. -FGD Building. -EconPile.

Boring To Pile #B13 -800mm dia. -FGD Building. -EconPile.

Bore Rig -HR240 -Hydraulic -Dismantling For Demobilization -EconPile.


MLT -Pile # B57 -1200mm dia. -Boiler -To Commence On 14.11.2011 -1141Ton. -EconPile.

Concreting To Pile #T249 -1000mm dia. -Turbine Hall -SynoHydro.

MCB -Area -Preparation To Commence With Bore Pile Works -800mm dia. -96Points -SynoHydro.

BOP -MCWS -Backfilling In Progress.