12.04.2012

 Chimney-Steel Fixing Top Bar of the Base Foundation in Progress
  Chimney-Steel Fixing Top Bar of the Base Foundation in Progress
Fuel Gas Duct-Pipe Ducts-Preparation of  Bored Pile Surrounding Prior for Concreting
 F11-Boiler-Formworks Installation of Stumps in Progress
 F4-Boiler-Final Preparation of Stumps Prior for Concreting and Backfilling in Progress
  F9-Boiler Final Preparation of Stumps Prior for Concreting

GL BK-BM / GL B9-B12.5-Boiler- Backfilling in Progress
 Mill-South Side-Backfilling in Progress
Mill B-Mechanical-Scaffolding Erection in Progress
 Turbine Hall-West Side-Steel Fixing of Base Foundation in Progress
 Turbine Hall-North Side-Steel Fixing of Ground Walls in Progress
Turbine Hall-South Side-Excavation in Progress
 Central Electrical Building-GL A-G / GL 2- Final Preparation on Base Foundation Prior for Concreting in Progress
  Central Electrical Building-GL A-G / GL 3- Steel Fixing of Base Foundation in Progress

Boiler-East Side-Mechanical-Temporary Laydown Area for Boiler Steel Structure
 Phase 1-Main Cooling Water-Preparation Prior for Steel Fixing of Base Foundation in Progress
 Phase 1-Seawater Fuel Gas Desulfurization Glass Reinforced Pipes-2nd Layer-Backfilling and Compaction in Progress
 New HV Line-Pylons-Near Existing Switchyard-Steel Frame Erection in Progress
New HV Line-Pylons-Inside 25 year Ash Pond-Steel Fixing of Base Foundation in Progress





10.04.2012

Chimney-Steel Fixing of Top Bars for the Base Foundation in Progress
 F4-Boiler-Formworks Installation of Stumps in Progress
 F5-Boiler-Final Preparation Prior for Concreting in Progress
 Ash Hopper-Casting of Lean Concrete Completed and Preparation for Steel Fixing
 F8-Boiler-Steel Fixing of Base Foundation in Progress
 F10-Boiler-Steel Fixing of Base Foundation in Progress
F9-Boiler-Backfilling in Progress and Formworks Installation of Stumps in Progress
 Mill-Mechanical-Packer Plates Installation in Progress
 Mill F to H-South Side-Backfilling in Progress
Mill C-Mechanical-Scaffolding Erection in Progress
 Turbine Hall-South Side-Excavation in Progress
 Turbine Hall-South Side-Preparation Prior for Lean Concreting
Turbine Hall-South Side-Hacking of Bored Piles in Progress
 Central Electrical Building-Steel Fixing of Column Starter Bar in Progress
 Central Electrical Building-Preparation Prior for Lean Concreting  in Progress



09.04.2012

 Chimney-Steel Fixing of Top Bars and Formworks Installation of Base Foundation in Progress
Fuel Gas Duct-Duct Pipes-Excavation of Bored Piles in Progress
 F10-Boiler-Cleaning Prior for Steel Fixing of Base Foundation
 F5-Boiler-Final Preparation of Stumps Prior for Concreting
 F9-Boiler-Removal of Stump Formworks
F11-Boiler-Casting Completed and Curing in Progress
 F4-Boiler-Removal of Formworks in Progress
Boiler Ash Pit- Final Preparation Prior for Final Pour
 Mill D-Mechanical-Scaffolding Erection in Progress
 Mill A & B-Retaining Wall-Formworks Removal in Progress
Mill H-Mechanical-Packer Plates Installation in Progress
 Ash Hopper-Boiler-Preparation Prior for Lean Concreting
 Turbine Hall-South Side-Preparation Prior for Hacking of Bored Pile
 Turbine Hall-East Side-Box Tie In Installation in Progress
Turbine Hall-Tower Crane Installation in Progress
 Central Electrical Building- Formworks Installation in Progress
 Central Electrical Building- Steel Fixing Installation in Progress
 Phase 1-Main Cooling Water-Excavation and Cutting of Spun Piles in Progress
 Phase 1-Sea Water Fuel Gas Desulfurization-Glass Reinforced Pipes-Compaction in Progress