01.03.2012

Mill-H.

Joint Inspection -J-Bolts -Positioning & Elevation -F7 -Stumps.

F4-Type A -Boiler -West Side -Curing In Progress.

Mill-Pedestal -B7-BB -Formwork Installation.

Mill-Pedestal -B1-BB -Steel Fixing In Progress.

Turbine Hall -Raft Foundation -Grid9 -Grid 3 -B-D -Steel Fixing -Bottom Layer.

Turbine Hall -Raft Foundation -Steel Fixing -Bottom Layer.(-3.6MLSD).

Turbine Hall -Raft Foundation -Steel Fixing -Bottom Layer (-3.6MLSD).

Chimney -BOP -Excavation In Progress.

Mill-Pedestal -B13-BB -Ready For Concreting.

Mill Pedestal -B11-BB -Final Inspection Prior Concreting.

MILL-G -Final Preparation Prior Concreting.

MILL-G -Final Preparation Prior Concreting.

Chimney -BOP -Excavation -Preparation For Lean Concrete In Progress.

29.02.2012

FGD -Pipes -Soil Improvement -Spun Pile -600mm dia.

F4-Type A -Boiler-West Side -Ready For Concreting.

F10-B4-Boiler -East Side -Concreting In Progress.

F4-Type-A -Boiler -West Side -Final Inspection Prior Concreting.

F4-Type A -Boiler -West Side -Final Inspection Prior Concreting.

Mill-E -Setting Up Of Frame Support.

Mill-G -Formwork Installation In Progress.

F4-Type A -Boiler -West Side -Concreting In Progress.

F4-Type A -Boiler -West Side -Concreting In Progress.

F7-Boiler -East Side -Stump -Adjustment Of Positioning/Leveling -J-Bolts.

27.02.2012

Site Office Preparation -EverShendai.

Waste Water Pit -Boiler -East Side -Base Preparation In Progress.(6m x 6m x 3.9m)

Mill-G -Installation Of J-Bolts.

F10-B4 -Boiler -West Side -Curing In Progress.

Turbine Hall -Grid 4 -Grid -3 -Preparation For Lean Concrete -(-3.6MLSD).

Turbine Hall -Hacking Of Piles In Progress -Grid 5 -Grid 4 -B/D.

Turbine Hall -Raft Foundation -Grid 9 -Grid 4 -B-D -Steel Fixing -Bottom Layer.

Turbine Hall -Steel Fixing -Bottom Layer -Raft Foundation -Grid -9 -Grid -4 /B-D.(-3.6MLSD).

Mill-G -Installation Of Formwork In Progress.

Mill-G -Installation Of Formwork In Progress.

F3-Boiler -East Side -Stump -Final Inspection Prior Concreting.

F1-Boiler West Side -Backfilling & Compaction.

26.0212

 Murray Roberts - Offshore Culvert Section Storage & Offices
 Offshore Culverts (approx.360 tons each) with small 4x4 for scale.
 Culvert Production Line Fig.1 - 8 No. Casting Stations
 Culvert Production Line Fig.2 - 8 No. Casting Stations

 Murray Roberts - Offshore Dredging Operations & Support Boats
 SWFGD GRP Trench (Left) & MCW  (Right) Trench under new HV Lines 
to East of Existing Station on Reclaimed land
 PDA Testing on Chimney Piles
 TMBJ Land Reclamation To East of Existing Switch Yard
 Completed Boiler Mill Foundation H - Stripped of Formwork Stripped 
& Template awaiting Transfer to Mill Foundation F.
Turbine Hall Foundation - Central East Portion prepared for blinding concrete.

24.02.2012

 Installation of First Alstom 400mm Dia Spun Pile for SWFGD GRP Piping Soil Improvement - Absorber Area. 

 Welding Inspection/ Surveillance By Client & Consortium for Spun Pile installation 
(Alstom Scope Spun Piles are Non-Load Bearing - For Soil improvement only) 

 Turbine Hall Foundation - Bottom Layer of Reinforcement and works in progress.

 Boiler Mill Foundation H on right of picture (Cast now Curing) & G on left of picture awaiting installation of bolts.Template frame will move to Mill F on 25/02/12

TMBT Piling & Civil Works Contractor commenced piling for new
 HV Transmission Tower Foundations.