FGD -Pipes -Soil Improvement -Spun Pile -600mm dia.
F4-Type A -Boiler-West Side -Ready For Concreting.
F10-B4-Boiler -East Side -Concreting In Progress.
F4-Type-A -Boiler -West Side -Final Inspection Prior Concreting.
F4-Type A -Boiler -West Side -Final Inspection Prior Concreting.
Mill-E -Setting Up Of Frame Support.
Mill-G -Formwork Installation In Progress.
F4-Type A -Boiler -West Side -Concreting In Progress.
F4-Type A -Boiler -West Side -Concreting In Progress.
F7-Boiler -East Side -Stump -Adjustment Of Positioning/Leveling -J-Bolts.