27.02.2012

Site Office Preparation -EverShendai.

Waste Water Pit -Boiler -East Side -Base Preparation In Progress.(6m x 6m x 3.9m)

Mill-G -Installation Of J-Bolts.

F10-B4 -Boiler -West Side -Curing In Progress.

Turbine Hall -Grid 4 -Grid -3 -Preparation For Lean Concrete -(-3.6MLSD).

Turbine Hall -Hacking Of Piles In Progress -Grid 5 -Grid 4 -B/D.

Turbine Hall -Raft Foundation -Grid 9 -Grid 4 -B-D -Steel Fixing -Bottom Layer.

Turbine Hall -Steel Fixing -Bottom Layer -Raft Foundation -Grid -9 -Grid -4 /B-D.(-3.6MLSD).

Mill-G -Installation Of Formwork In Progress.

Mill-G -Installation Of Formwork In Progress.

F3-Boiler -East Side -Stump -Final Inspection Prior Concreting.

F1-Boiler West Side -Backfilling & Compaction.