14.02.2012

Mill-H -Adjusting And Leveling Of J-Bolts In Progress.

Mill-H -Setting And Leveling Of J-Bolts In Progress.

F3-Boiler -West Side -Stump -Inspection Of J-Bolts Positioning.

F3 -Boiler-West Side -Stump -Inspection Of J-Bolts Positioning.

Pile #HN18 -1200mm dia. -Installation Of Steel Cage -Chimney-BOP -SinoHydro.

Spun Piles-400mm dia. -FGD -Pipes -Soil Improvement.

Piling Rig -Preparation For 400mm dia. -Spun Pile -FGD -Pipes -Soil Improvement.

F4 -Type D -Boiler -West Side -Installation Of Formwork.

F11-B14 -Boiler -East Side -Final Inspection Prior Casting.

Turbine Hall -Level (-3.6MLSD).

Turbine Hall -Grid 9 -Grid 8 -B/D -(-3.6MLSD) -Carting Away Of Hacked Piles.

Turbine Hall -Grid 5 -Grid -4 -B/D -(-3.6MLSD) -Preparation For Lean Concrete.

F11 -B14 -Boiler -East Side -Concreting In Progress.

13.02.2012

F3 -Boiler -East Side -Steel Reinforcement-Stump- (Final Preparation) Prior Inspection.

F6 -Type A -Boiler -West Side -Curing In Progress.

Mill -C -Cleaning/Brushing To Steel Reinforcement.

F11-B14 -Boiler -East Side -Preparation For Steel Fixing -Stumps.

Mill -H -Adjusting/Leveling To J-Bolts In Progress -Prior Final Inspection.

Mill -H -Adjusting/Leveling To J-Bolts In Progress Prior Final Inspection.

Turbine Hall -Grid 9 -Grid 8 -B-D .

Mill -B -Brickwall Formwork In Progress.

F4-Type D -Boiler -West Side -Steel Reinforcement -Pile Caps.

Boring To Pile #HN53-1200mm dia. -Chimney -BOP -EconPile.

Preparation For Spun Pile 400mm dia. -Soil Improvement -FGD Pipes.

Pile #HN03-1200mm dia. -Chimney-Installation Of Steel Cage -SinoHydro.

Concreting To Pile #HN53-1200mm dia. -Chimney -BOP -EconPile.

F11-B14 -Boiler -East Side -Final Preparation Prior Casting.

Mill -D -Hacking/Chipping -Preparation For Construction Joint -2nd Stage Pour.

Turbine Hall -Excavation To Condensate Tank -Down To Level (-7.2MLSD).

10.12.2012

F10-B4 -Boiler -West Side -Hacking Of Piles In Progress (12nos).

F6 -Boiler -West Side -Steel Fixing -Stump.

F6-Type A -Boiler -West Side -Ready For Concreting.

F11-B14 -Boiler -East Side -Inspection Of Steel Reinforcement -Bottom Layer.

F11-B14 -Boiler -East Side -Steel Reinforcement.

F11 -B14 -Boiler -East Side -Inspection Of Steel Reinforcement -Bottom & Top Layer.

Mill -H -Final Setting To J-Bolts Prior Inspection.

Turbine Hall -Sheet Piling -Condensate Sump Pit.

F3 -Boiler -West Side -Inspection of Steel Reinforcement -Stump.

Turbine Hall -Lean Concrete Preparation -Grid 8 -Grid -7 -B/D.(-3.6MLSD).

Turbine Hall -Condensate Sump Pit -Excavation In Progress -Down To Level (-7.2MLSD).

F4 -Type-A -Boiler -West Side -Steel Fixing In Progress.

09.02.2012

F4 -Type A -Boiler -East Side -Steel Fixing In Progress.

F6 -Type A -Boiler -East Side -Final Preparation Prior Concreting.

F10-B4 -Boiler -East Side -Hacking Of Piles (12nos) In Progress.

F1-B4 -Boiler -West Side -Curing In Progress.

Mill -H -Preparation To Install J-Bolts.

F11-B14 -Boiler -East Side -Steel Reinforcements -Top Layer.

Turbine Hall -Sheet Piling To Condensate Sump Pit In Progress.

Mill -H -Pedestal -Installation Of J-Bolts In Progress.

Mill-H -Installation Of J-Bolts In Progress.

Mill-H -Installation Of -J-Bolts In Progress -8nos.

Turbine Hall -Excavation -3rd Stage -Down To Level (-3.6MLSD).

Turbine Hall -Gridline 8 -Gridline 6 -B/D -Preparation For Lean Concrete -(-3.6MLSD).