17.11.2011

Consortium Office.

Weekly EHS Tool Box Meeting -ALSTOM/CMC/MCB/GIGA.

Boring To Pile #B12-800mm dia. -FGD -EconPile -Last Point For EconPile.

Excavation -Boiler Type F3 -Foundation -West Side.

Steel Fixing -Bunker/Mill -1st Pour Foundation -B9.

Bunker/Mill -Pile Cap -B15.

Boiler -Type F3-West Side -Foundation -Excavation In Progress. -

Boiler -Type F3-West Side- Foundation -West Side -Excavation In Progress.

Steel Fixing/Formwork -Bunker/Mill -1st Pour Foundation -B9.

Steel Fixing -Bunker Mill -1st Pour Foundation -B11.

Cleaning Of Debris -Hacked Piles -Bunker/Mill -B15.

16.11.2011

Boring To Pile #B11-800mm dia. -FGD -EconPile.

Installation Of Dewatering Pipes -Boiler -North/East Side.

Sheet Piling -Boiler -Type F3/F6 -Foundation -West Side -Preparation For Coffer Dam.


Hacking Of Piles -Bunker/Mill -Foundation -B15.

Boiler -Type F3/F6 -Foundation -West Side -Excavation In Progress.

Consortium Office -Installation Of Purlins -Roofings -In Progress.

Consortium Office -Alstom -Laying Of Bricks -Grd. Floor.

Consortium Office -Alstom -Concreting To Appron Slab.

Steel Fixing -Bunker/Mill -1st Pour Foundation -B9.

Steel Fixing -Bunker/Mill -1st Pour -Foundation -B9.

Installation Of Steel Cage -Pile #B32-800mm dia. -Main Control Building -SinoHydro.

Boring To Pile #B38 -800mm dia. -Main Control Building -SinoHydro.

15.11.2011

Consortium Office -Alstom -Laying Of Bricks -Grd. Floor.

Installation Of Dewatering Pipes -Boiler -East Perimeter -87/120 points.


Installation Of Dewatering Pipes -Boiler -East Perimeter.

Sheet Piling To Boiler -Type F3/F6 -Foundation -Preparation Of Coffer Dam.

MLT -In Progress -Pile #B57-1200mm dia. -Boiler.1141Ton.

Hacking Of Piles -Bunker/Mill -B13.

Pile Cap -Bunker/Mill -B9 -Pending PIT -Proceed With Steel Reinforcement Installation.

Preparation Of Bar Bending Yard -Boiler -Type F3/F6 -Foundations.

Excavation For Dewatering Discharge Drainage(Boiler -North Side) To Silt Trap Area.

Concreting To Pile #B08 -800mm dia. -FGD -EconPile.

Concreting To Pile #B16 -800mm dia. -FGD -EconPile.

14.11.2011

Consortium Office -Alstom -Laying Of Bricks In Progress.

Hacking Of Piles -Bunker/Mill -B11.

Bunker/Mill -B9 -Preparation For PIT & Steel Reinforcement Installation.

Applying Of Curing Compound -Bunker/Mill -1st Pour Foundation -B7.

Applying Of Formwork Oil -Preparation For Bunker/Mill -1st Pour -B9.

Lean Concrete -Bunker/Mill -B13.

Excavation To Boiler Area -East Side.

Installation Of Dewatering Pipes -Boiler -East Perimeter -87/120 Points Completed.

Consortium Office -Laying Of Bricks In Progress.

Consortium Office -Alstom -Laying Of Bricks In Progress.

Consortium Office -Alstom -Laying Of Bricks/Installation Of Door Frames/Preparation Of Mock-Up Unit In Progress.


Concreting To Pile #B15-800mm dia. -FGD -Econpile.

MLT -Pile #B57 -1200mm dia. -Boiler In Progress -1141Ton.

MLT -Pile #B57 -1200mm dia. -Boiler -In Progress =1141Ton.

Site Office -Murray Robert -Off-Shore Works/Water Intake.

Sheet Piles -Preparation Works -Water Intake/Off-Shore Works -Murray Robert.