Chimney Foundation Bored Piling - 56/56 No. (CMC)
Boiler Foundation Pedestal - Main Steel Structure Bolts (75mm) installed
Boiler Foundation Type F10 (East) - Form work in progress.
Turbine Hall Foundation - Preparation for installation of reinforcement.
Turbine Hall Foundation - Pile trimming
Turbine Hall Foundation - Pile trimming
Turbine Hall Foundation - Condensate Pump Sumps Stage 1 - Deep excavation works
Turbine Hall Foundation - Condensate Pump Sumps Stage 1 - Deep excavation works
Boiler Foundation Bunker Mill Steel Structure Pedestal - Pre Pour Inspections
Boiler Mill Foundation G - Cleaning of reinforcement
Boiler Mill Foundation H - Final Concrete Pour.