Boiler Mill Foundation H Formwork Complete (North)
Boiler Mill Foundation H & Mill Motor Cantilever Formwork Complete (South)
Boiler F10 Foundation Rebar Complete
Boiler Mill Foundation F - Final Construction Joint Preparation
Turbine Hall Foundation - Pile Trimming & Preparation for installation of Reinforcement.
Turbine Hall Foundation - Condensate Pump Sump Deep excavation works
Chimney Foundation - Pile Bore - 55 of 56 No. (CMC)
Extraction of Boiler F3/7 West Sheet Piles for use in GRP trench under new HV lines
Boiler Mill Foundation H - Pre Pour Inspections & Bolt Survey
Boiler Mill Foundation H - Pre Pour Inspections & Bolt Survey
Boiler Mill Foundation H - Pre Pour Inspections & Bolt Survey
Boiler Mill Foundation H - Pre Pour Inspections & Bolt Survey
Boiler Mill Foundation H - Pre Pour Inspections & Bolt Survey
Boiler Foundation Type F3 West - Pedestal Rebar Inspection Pre Formwork.
Boiler Foundation Type F6 East - Back Filling & Compaction