Concreting To Pile #A65-1000mm dia. -Absorbers Foundation -SinoHydro.
Sheet Piling -Coffer Dam -F5 -Type E -Foundation -Boiler.
F3 -Preparation To Commence With Steel Fixing -Bottom Layer.
F7 -Boiler -East Side -Steel Fixing In Progress -Scheduled For Castin On 14.01.2012.
Bunker/Mill -North Side -B17-B13 -BB -Backfilling & Compaction In Progress.
Bunker/Mill -B17 -North Side -Backfilling In Progress.
Mill -H -Preparation For Re-Bar/J-Bolts & Concreting -2nd Phase.
PIT -F3 -Boiler -East Side.
BOP -Sub-Station -Project Power Supply -Concreting To Base Slab.
Fabric Filter -Final Inspection Prior Concreting.-Grid 1 -Grid 3.
Boring To Pile #A86-1000mm dia. -Absorbers Foundation -EconPile.
BOP -MCWS -Reclaimation Area -Preparation To Commence With Piling Works -Spun Pile.
BOP -Coal Yard Stack & Reclaimer -MLT In Progress.
BOP -Coal Yard -Test Piling -600mm dia. -Spun Pile .
Fabric Filter -Concreting To Pile Caps & Tie Beams -Grid 1 -Grid 3.
Installation Of Steel Cage -Pile #A14-1000mm dia. -Absorbers Foundation -SinoHydro.
Fabric Filter -Concreting To Pile Caps & Tie Beams -Grid 1 -Grid 3.