11.01.2012

Boring To Pile #A42-800mm dia. -Absorbers Foundation -EconPile.

Fabric Filter -Grid -7 -Grid 8 -Excavation In Progress.

F3 -Boiler -East Side -Steel Fixing -Bottom Layer.

F7 -Boiler -East Side -Installation Of Formwork In Progress.

Bunker/Mill -G -Brickwall Formwork In Progress.

Bunker/Mill -B3 -BB -Steel Fixing In Progress.

CEB -Hacking Of Piles In Progress -(7/12).

CEB -Excavation Completed -Pending Dewatering/Hacking Of Piles.

F1 -Type F -Boiler -West Side -Curing In Progress.

Installation Of Vermiculite & Plug -Pile #A37-1000mm dia. -Absorbers Foundation -EconPile.

Concreting To Pile #A37-1000mm dia. -Absorbers Foundation -EconPile.

F3 -Boiler -East Side -Steel Fixing -Bottom Layer In Progress.

Consortium Office -Alstom -Grd.Floor.

Consortium Office Alstom.

Consortium Office -CMC.

Consortium Office -Alstom -1st Floor -Installation Of Vinyl Tiles.