Chimney -BOP -Excavation In Progress.
Waste Water Pit -Boiler -East -Compaction Of Crusher Run.
Mill -E -Preparation For J-Bolts Installation.
F1-Type F -Boiler -West Side -J-Bolts -Stump.
Turbine Hall -Grid 3 -Grid 2 -B-D -Preparation For Lean Concrete.
Turbine Hall -Steel Reinforcement -Raft Foundation -Bottom Layer.
Turbine Hall -Steel Reinforcement -Raft Foundation -Bottom Layer.
Turbine Hall -Steel Reinforcement -Raft Foundation -Bottom Layer.
Mill Equipments -Pulverizer -Delivery.
Mill Equipments -Pulverizer.
GRP -FGD -Pipes -Laydown Area.
Mill-G -Final Inspection Prior Concreting.