02.03.2012

Chimney -BOP -Excavation In Progress.

Waste Water Pit -Boiler -East -Compaction Of Crusher Run.

Mill -E -Preparation For J-Bolts Installation.

F1-Type F -Boiler -West Side -J-Bolts -Stump.

Turbine Hall -Grid 3 -Grid 2 -B-D -Preparation For Lean Concrete.

Turbine Hall -Steel Reinforcement -Raft Foundation -Bottom Layer.

Turbine Hall -Steel Reinforcement -Raft Foundation -Bottom Layer.

Turbine Hall -Steel Reinforcement -Raft Foundation -Bottom Layer.

Mill Equipments -Pulverizer -Delivery.

Mill Equipments -Pulverizer.

GRP -FGD -Pipes -Laydown Area.

Mill-G -Final Inspection Prior Concreting.