29.03.2012

 Chimney-Steel Fixing-Bottom Layer Base Foundation in Progress

 Condensate Pump Pit-Curing Of Concrete
 Fabric Filter-Compaction at East Side in Progress
 F2-Boiler-Formworks Removal in Progress
 F5-Boiler- Steel Fixing and Formworks Installation in Progress
 F4-Boiler- Steel Fixing and Formworks Installation in Progress 
 F2-Boiler- Final Preparation Prior to Concreting


 F1-Boiler- Backfilling and Compaction in Progress
  F9-Boiler- Steel Fixing and Formworks Installation in Progress 
 Boiler Ash Pit-Final Preparation Prior to Concreting
  
 F8-Boiler- Preparation for Lean Concreting
 Mill A-Final Preparation Prior for Concreting
  Mill A-Final Preparation Prior for Concreting
 Turbine Hall- Steel Fixing and Formwork Installation in Progress
  Turbine Hall- Steel Fixing and Formwork Installation in Progress
 Central Electrical Building-Final Preparation Prior for Lean Concreting
 Phase 3-Main Cooling Water-Spun Piles Delivery
 Phase 1-Main Cooling Water- Excavation in Progress
Phase 1 Flue Gas Desulfurization-GRP-Backfilling in Progress  
 Mill-Retaining Wall South Side-Concrete Curing of Base Foundation
 Mill-Retaining Wall South Side-Wall Formworks Installation in Progress
 Mill South Side-Backfilling in Progress
 F11-Boiler-Concrete Curing of Stumps
 Fuel Gas Duct- Preparation of Bored Pile Prior for Concreting
Eversendai-Site Office Construction in Progress 
Boiler-Material Delivery 1st Batch of Boiler Duct 
Boiler-Material Delivery 1st Batch of Boiler Duct 










28.03.2012


 Flue Gas Duct-Bored Pile-Excavation in Progress 
 Eversendai-Site Office Construction in Progress
 Chimney-Steel Fixing-Bottom Layer Base Foundation in Progress
Fabric Filter-Backfilling and Compaction in Progress 
 Flue Gas Duct-Bored Pile-Preparation for Excavation in Progress 
 F5-Boiler-Formworks Installation in Progress
 F1-Boiler-Backfilling and Compaction in Progress
F4-Boiler-Formworks Installation and Backfilling and Compaction in Progress
F4-Boiler-Formworks Installation  in Progress
Boiler Ash Pit-Formworks Installation in Progress
F9-Boiler-Steel Fixing in Progress
F11-Boiler-Final Preparation Prior to Concreting
 Mill B- Formworks Removal in Progress
Condensate Pump Pit-Formworks Installation in Progress
F6-Boiler-Final Preparation Prior to Concreting
Mill A-Steel Fixing and Formworks Installation in Progress
Mill A-Steel Fixing and Formworks Installation in Progress
Turbine Hall-Steel Fixing and Formworks Installation for Raft Foundation in Progress
Turbine Hall- Hacking of Piles in Progress South Side
Central Electrical Building-Preparation for Lean Concrete
Phase 1-Flue Gas Desulfurization-Backfilling in Progress
Phase 4-Main Cooling Water-Sheet Piling in Progress
Phase 1-Main Cooling Water (MCW)-Excavation in Progress


Mill G & H-Retaining Wall-Steel Fixing and Formworks Installation in Progress
F11-Boiler-Removal of Debris and Preparation for Lean Concreting