Laying Of Bentonite Pipes -From Pond To Turbine Hall Area -Synohydro.

Installation/Setting Up Of Bore Rig # 5 -Hydraulic Unit.


Backfilling Works -MCWS -Pipes/Box Culvert Area.

Unloading Of Sheet Piles -For Bunker/Boiler/Turbine Hall -Prior De-Watering/Excavation For Foundation.

Excavation -Prior Commencement Of Bore Pile Works -Turbine Hall.

Survey /Setting Out Works -MCW -Pipes Area -Backfilling Works.

Ground Beam Preparation -Consortium Office.