07.12.2011

Consortium Office -Alstom.

Installation Of Formwork -Type F6-Foundation -Boiler -West Side -Scheduled For Concreting On 09.12.2011 @180cu.m.

Steel Fixing -Type F3 -Foundation -Boiler -West Side.

Bunker/Mill -Compaction Works -Preparation For FDT.

Bunker/Mill -Preparation For FDT.

Compaction -Bunker/Mill -Preparation For FDT -B11 -B3.

Hacking Of Piles -Bunker/Mill -B15.

Excavation To Boiler Area -F3/F7 -East Side.

Fabric Filter -West Side -Preparation For Lean Concrete.

Inspection Of Steel Reinforcement -(Bottom Layer) -Type F3 -Foundation -Boiler -West Side.

Inspection Of Steel Reinforcement -(Bottom Layer) -Type F3 -Foundation -Boiler -West Side.