Consortium Office -Alstom.
Installation Of Formwork -Type F6-Foundation -Boiler -West Side -Scheduled For Concreting On 09.12.2011 @180cu.m.
Steel Fixing -Type F3 -Foundation -Boiler -West Side.
Bunker/Mill -Compaction Works -Preparation For FDT.
Bunker/Mill -Preparation For FDT.
Compaction -Bunker/Mill -Preparation For FDT -B11 -B3.
Hacking Of Piles -Bunker/Mill -B15.
Excavation To Boiler Area -F3/F7 -East Side.
Fabric Filter -West Side -Preparation For Lean Concrete.
Inspection Of Steel Reinforcement -(Bottom Layer) -Type F3 -Foundation -Boiler -West Side.
Inspection Of Steel Reinforcement -(Bottom Layer) -Type F3 -Foundation -Boiler -West Side.