08.05.2013

 Boiler - Pressure Parts
Boiler - Coal Piping
Boiler - Main Steam Piping @ 64M lvl
 Boiler - Cable Tray @ 51M lvl
 STH - ST/Gen Table @ 16M lvl
 STH - Cable Trunking Hi-bay Lighting
 STH - Cable Tray @ 0M lvl
 STH - CCW Piping @ 0M lvl
 STH - Condenser Area 
 STH - Heat Exchanger Area
 STH - Cable Tray Ladder @ -5.2M lvl
 STH - Floor Slab @ 16M lvl
 Stator Lifting Frame Area
 MCW Saddle North Side of STH - Looking West
 Condensate Make Up Tank - Looking North
 CEB - Battery Room 
 CEB - Blockwork @ 20M lvl
 Main Transformer Area - Looking Southeast
 FF and FGD - Looking North
 Booster Fan - Looking Southeast
 BEB - Cable Tray @ 0M lvl
BEB - Blockwork @ 4M lvl
 BEB, Compressor Area and Bottom Ash Silo - Looking North
 Fly Ash Silo - looking North
 Service/Fire Water Pumphouse & Tanks - Looking East
 Crusher/Screening House - Looking Northwest
 Coal Yard Transfer Tower #10 - Looking Northwest
 Aeration Basin - Looking Southeast
Land Reclamation Progress for VO 11 & 13, & the New 5-Year Ash pond