| Power Block Northwest Side |
| Boiler Backpass Hanger Rods Support Structure and Boiler Walls |
| Boiler - LBC Piping and Support Works @ 45m Level |
| STH - Lube Oil Room Rebar work |
| STH - Roofing Looking West |
| STH - ST / Gen Table |
| Central Electrical Building |
| Central Electrical Building @ 0m level |
| Central Electrical Building @ 4m level |
| Central Electrical Building @ 4m level |
| Main Transformer Area- Looking East |
| Fabric Filter - Looking North |
| FGD_RGP and MCW Pipes - Looking Southeast |
| Aeration Basin and CW Discharge Trench - Looking Southeast |
| Service/Fire/Potable tank foundation - looking east |
| Demin Water Plant and Tanks Foundations |
| Bottom Ash Silo |
| Condensate Make up Tank - Looking North |
| Fly-ash Silo Foundation |
| FGD Area Slab - Northside |
| Booster Fan - Looking Southwest |
| FGD Area Slab - Southside |
| Dinner Function with Mr. Joseph Chriqui |
| Dinner Function with Mr. Joseph Chriqui |