Chimney -Lean Concrete And Preparation For Pile Hacking.
FGD -Pipes -Spun Pile -400mm dia. -Soil Improvement -1st Phase.
Waste Water Pit -Boiler -East Side -Steel Reinforcement.
150T Crane -EverShendai -Preparation For Installation Of Pulverizer -Mill-H.
Mill-D -Installation Of Formwork.
F5-Boiler -Lean Concrete In Progress.
Fabric Filter -Steel Fixing -Stump.
Preparation For Installation Of Pulverizer -Mill-H.
Mill-F -Curing In Progress.
Installation Of Pulverizer -Mill -H.
Installation Of Pulverizer -Mill-H.
Erection Of Site Office -EverShendai.