21.09.2011

Preparation For Load Test (MLT) -Pile Point # B93-800mm dia. -Boiler.

Finishing Works To Base Slab-Consortium Office -CMC.

Final Preparation Prior Concreting To Base Slab -Consortium Office -Alstom.

Concreting To Ground Beam -Consortium Office.

Concreting (Build-Up) To MLT Pile Point # B82-1000mm dia. -Boiler.

Concreting To 1st Pile For Synohydro @ Turbine Hall -Pile # T241 -1000mm dia.

Turbine Hall -Bore Pile Working Area -Synohydro.