16.09.2011


Sino Hydro start jib assembly of 4 N0. new BG 25 rigs.
Bauer Customer support on site to assist.


All kentelage deliveries complete and placed for first MLT testing


Econpile continue to progress Boiler, now 64% complete.


Turbine Hall Excavation to Pile mat level complete.
Sino Hydro due to start piling 18/09