25.11.2011

Hacking Of Piles -Type F6 -Foundation -Boiler -West Side.

Curing To Bunker/Mill -Foundation -B13 -1st Phase Pour.

Final Inspection -Bunker/Mill -Foundation -B15 -1st Phase Pour -Prior Concreting.

Concreting To Bunker/Mill -Foundation -B15 -1st Phase Pour.

Concreting To Pile #T170-1000mm dia. -Turbine Hall -SinoHydro.

Boring To Pile #A15-800mm dia. -CCB -SinoHydro.

Lean Concrete Preparation -Bunker/Mill -Foundation -B1/BB.