22.10.2011

Excavation To Boiler Area.

Steel Reinforcement Preparation -Bunker/Mill -Pile Cap.

PIT -Test -Bunker/Mill -Pile#A75/A05/A06/A07/A08 -800mm dia.

Concreting To 1st Floor Slab -Consortium Office.

Laying Of BRC -1st Floor -Consortium Office.

SI Pontoon -Ash Pond -BOP.

Backfilling -MCWS.