09.09.2011

Steel Cage Fabrication -Bore Pile -Turbine Hall -Synohydro.

Excavation For Water Pipes -Consortium Office.

Steel Reinforcement -Ground Beams -Consortium Office.

Laying Of BRC -Base Slab -Consortium Office.

Laying Of BRC -Base Slab -Consortium Office.

Laying Of HDPE Pipe -50mm dia. -Water Supply To Consortium Office.

Formwork Fabrication For Ground Beams -Consortium Office.

MCWS -Pipes Area -Backfilling In Progress. -BOP.

Concreting To Pile # B54 -1200mm dia. -Boiler Area.

Project Sign Board.