03.07.2012

 Phase2_SWFGD_GRP-North of Chimney - Looking East
 Phase2_SWFGD_GRP-North of Chimney - Looking Southeast
 Fabric Filter -West Side- Looking Southeast
  Boiler Electrical Building - Looking Northwest
  Boiler-Structural Steel-East Side - Looking Southwest
 Boiler-Structural Steel-West Side - Looking Southeast
   Boiler-Structural Steel West Side- Looking Northeast
  Boiler-Structural Steel-East Side - Looking Northwest
   Boiler-Structural Steel and Steam Turbine Hall - Looking North
  Boiler Area - Looking South
   Boiler-East Side-Concrete Gully - Looking West
Ash Hopper - Looking West
Boiler-Electrical Pit # P205 - Looking West
   Steam Turbine Hall East Side- Looking Southwest



  Steam Turbine Hall-East Side - Looking North
 Steam Turbine Hall - Looking Northwest

    Steam Turbine Hall -South Side - Looking East
 Steam Turbine Hall-East Side-Concrete Slab @ 0.00M lvl 
  Steam Turbine Hall-West Side - Looking South
  Steam Turbine Hall-North Side - Looking East
 Steam Turbine Hall  - Looking Southeast
  Central Electrical Building - Looking North
  Central Electrical Building-East Side- Looking West
  Central Electrical Building-East Side-Electrical Conduit- Looking West
 ECS - Pre-fabrication of Hopper platform at laydown area
Clearing Works on going-East Side of the Plant

02.07.2012


Afternoon Photo_Site Currently Experiencing Heavy Rain - Looking South
Steam Turbine Hall 150 Ton O/H Crane Delivered to Manjung 4 Site.

 Steam Turbine Hall 150 Ton O/H Crane Delivered to Manjung 4 Site.

 Phase2_SWFGD_GRP-West of Chimney - Looking East
 Phase2_SWFGD_GRP-North of Chimney - Looking Northeast
 Fabric Filter -West Side- Looking Southeast
  Boiler Electrical Building - Looking Northwest
  Boiler-Structural Steel-East Side - Looking Southwest
 Boiler-Structural Steel-West Side - Looking Southeast
   Boiler-Structural Steel West Side- Looking Northeast
  Boiler-Structural Steel-East Side - Looking Northwest
   Boiler-Structural Steel and Steam Turbine Hall - Looking North
  Boiler-Structural Steel - Looking South
 Ash Hopper - Looking East
 Boiler-Electrical Pit # P205 - Looking West
    Steam Turbine Hall - Looking Southwest
  Steam Turbine Hall-East Side - Looking North
  Steam Turbine Hall - Looking Northwest
    Steam Turbine Hall -South Side - Looking East
  Steam Turbine Hall-West Side - Looking South
  Steam Turbine Hall-North Side - Looking East
 Steam Turbine Hall - Looking Southeast
  Central Electrical Building-East Side-Electrical Conduit- Looking West
 Central Electrical Building - Looking Northwest
 MCW-Beneath New HV Line - Looking Northeast
 MCW-Bet. New HV Line and Aeration Basin - Looking Southeast
 Coal Yard-Stacker Reclaimer-Spun Piles - Looking Northwest
 ECS - Pre-fabrication at laydown area
Client Tower Old HV Line-East Side of STH Hacking of Foundation - Looking East