22.02.2013

Main Transformer No.1 Delivered for off loading on to foundation. - Looking NW
Boiler, FGD Ducts, Booster Fans  and FF - Looking South
Boiler - Looking Southwest

Boiler - East Side
Boiler - 0m level

Boiler-Pressure Parts Wall and Pipe Headers
Boiler Area 2 Slab Concreting Works
Boiler - Looking Southeast

Steam Turbine Hall - Looking West
Steam Turbine Hall - Looking Northwest

Steam Turbine Hall-ST / GT Table - Looking North
Steam Turbine Hall - Looking East
Central Electrical Building - West Side
Central Electrical Building_MV Switchgear @ 4M Lvl

Central Electrical Building cable tray installation- 4m Level
Main Transformer Area- Looking East

Main Transformer Area - Main Transformer Rails
Main Transformer Area - Main Transformer Rails
Fabric Filter - Looking Northeast

SWFGD GRP Phase 3 and MCW Saddle
FGD Aeration Basin
MCW Pipe Trench at Reclaimed Existing 5 yr Ash pond

Service/Fire water storage tanks fdn works

Demin Water Treatment Plant  Fdn Works

Screening House - Looking Southwest

Fly Ash Silo Fdn

Booster Fan, Absorbers and FGD Foundation - Looking South