16.09.2011


Sino Hydro start jib assembly of 4 N0. new BG 25 rigs.
Bauer Customer support on site to assist.


All kentelage deliveries complete and placed for first MLT testing


Econpile continue to progress Boiler, now 64% complete.


Turbine Hall Excavation to Pile mat level complete.
Sino Hydro due to start piling 18/09

15.09.2011

Safety Tool Box Meeting -CMC/ALSTOM.

Bore Pile Area -Boiler & Ash Hopper.

Steel Cage Fabrication -Bore Pile Turbine Hall -Synohydro.

Bore Rigs -4nos. -Synohydro -To Be Utilized For Turbine Hall Bore Pile Works.

Concreting To Ground Beams -Consortium Office.

14.09.2011

Installation Of Steel Reinforcement -Ground Beams -Consortium Office.

MCWS -Backfilling Works -Piping Systems Area.


Concreting To Ground Beams -Consortium Office.

Concreting To Ground Beams -Consortium Office.

Removing Of Casing -Pile # D13-1000mm dia. -Ash Hopper.

14/09/2011


20 Artic's of MLT testing & SynoHydro piling equipment arrives over night.

Syno Hydro Bauer Piling Rigging start arrive on site.

Early morning toolbox talk with general Civil workers and Management.

video video

13.09.2011

Preparation Of Ground Beams -Consortium Office.

Installation Of Plug -Pile # D15 -1000mm dia. -Ash Hopper

Bore Pile -Area -Boiler /Ash Hopper.

Backfilling -MCWS -Area -Pipes System.

12.09.2011

Installation Of Pipes -Water Supply/Sewerage System -Consortium Office.

Steel Reinforcement -Ground Beams -Consortium Office.

Soil Investigation -BOP -Screening Hall.

Boring To Pile # B98 -1000mm dia. -Boiler.

Bore Pile Area -Boiler.

MCWS -Backfilling Works In Progress -BOP -Pipes System.

Concreting To Pile # B62-1200mm dia. -Boiler.

11.09.2011

Bar Bending -Steel Reinforcement Preparation -Ground Beams -Consortium Office.

Steel Reinforcement -Ground Beams -Consortium Office.

Steel Reinforcement -Ground Beams -Consortium Office.


Concreting To Pile # B85 -1000mm dia. -Boiler.

Bore Pile Area -Boiler.

10.09.2011

Safety Tool Box Meeting -CMC/MudaJaya/Econpile.

Steel Reinforcement -Ground Beams -Consortium Office.

Excavation For Pipes -Water Supply And Sewerage System -Consortium Office.

Steel Reinforcement -Ground Beams -Consortium Office.

Bore Pile Area -Boiler.

Steel Cages Preparation -Bore Pile -Turbine Hall -Synohydro.