04.09.2012

 Chimney - Looking Northwest
 Phase2_SWFGD_GRP-West of Chimney - Looking North
  Phase2_SWFGD_GRP-West of Chimney - Looking North
 Fabric Filter -East Side- Looking Northwest

  Boiler Electrical Building - Looking Northeast
 ID Fans East Side- Excavation - Looking South
 Boiler-Cavity Area - Looking South
  Boiler-East Side - Looking Northwest
  Boiler-2nd Coal Silo Cone Installation - Looking South
   Boiler-Ist Coal Silo Cone Installation - Looking North
  BOP Area-Spun Piling-East Side of Boiler - Looking North
 Steam Turbine Hall-South Side-Cooling Water Pipe (CWP) Saddle - Looking East
  Phase 3_MCW-Saddle Excavation - Looking Southeast
  Steam Turbine Hall-North Side-Cooling Water Pipe (CWP) Saddle Excavation - Looking East
  Steam Turbine Hall-East Side - Looking South
   Steam Turbine Hall-Structural Steel North Side - Looking Southeast
 Phase 4 SWFGD_GRP-Base Preparation - Looking North
 MCW-Bet. New HV Line and Aeration Basin - Looking North
 Piperack #10 @ the 5yr Ash Pond- Looking South
Aeration Basin-Spun Piling Works - Looking East